What US Steel Prices Mean for Data-Centre Budgets
A 17-week rally in American hot-rolled coil, driven by 50% Section 232 tariffs, is pushing data-centre construction costs to multi-year highs at the moment AI capital expenditure faces its sharpest investor scrutiny yet.โฆ

Photo: Willians Huerta / Pexels
As of 24 November 2026. This page reports business and market effects only. It takes no position on the events and makes no predictions. We update or remove it when the facts change.
Context: The United States raised its baseline Section 232 steel tariff from 25% to 50% in June 2025, covering the great majority of overseas steel shipments, a measure that has since restructured North American and global steel trade flows; Proclamation 11032, effective 8 June 2026, additionally made steel racks a dutiable derivative at 25%, according to NextMSC's component-cost research published on 1 October 2026. (NextMSC, 1 October 2026)
The Price Rally and Its Scale
Procurement Resource reported on 19 November 2026 that Nucor lifted its US hot-rolled coil consumer spot price by US$15 to US$1,295 per short ton on 9 November, the 17th consecutive weekly increase, with its California Steel Industries joint-venture price rising in parallel to US$1,365 per short ton. US spot hot-rolled coil was indicated in a band of US$1,340 to US$1,400 per short ton on 6 November 2026, against US$825 to US$865 per short ton a year earlier โ a year-on-year increase of roughly 52%. Procurement Resource attributed the sustained hike to Section 232-constrained import supply, producer pricing discipline and a thin pool of available spot tonnage. (Procurement Resource, 19 November 2026)
Nucor Corporation's third-quarter 2026 earnings release, filed with the US Securities and Exchange Commission on 26 October 2026, recorded consolidated net earnings attributable to stockholders of US$1.32 billion (US$5.80 per diluted share), against US$607 million (US$2.63 per diluted share) in the third quarter of 2025 โ a 117.5% increase year on year. Net sales reached US$11.25 billion and EBITDA US$2.28 billion. The steel mills segment alone contributed US$1.788 billion in pre-tax segment earnings for the quarter, up from US$793 million a year earlier. Nucor's Q3 2026 earnings call transcript, published by The Motley Fool on 27 October 2026, noted that data centres represent approximately 15% of the company's total backlog. (US Securities and Exchange Commission (Nucor 8-K), 26 October 2026; The Motley Fool, 27 October 2026)
The structural steel producer price index rose 23.9% between October 2025 and August 2026, according to NextMSC's October 2026 analysis, which drew on US Bureau of Labour Statistics and Federal Register data. US data-centre construction was running at a seasonally adjusted annual rate of US$50.7 billion as of April 2026, the same analysis noted. (NextMSC, 1 October 2026)
What the Squeeze Costs Hyperscale Developers
Terrapin Construction Group, in an analysis published on 6 November 2026, put the benchmark US data-centre construction cost at US$10 million to US$13 million per megawatt of IT load in 2026, with AI-optimised, high-density facilities running US$20 million to US$37 million per delivered megawatt โ roughly three times a conventional build. Structure and envelope account for 10% to 15% of total project cost, meaning the structural steel component, while not the dominant budget line, is exposed directly to the tariff-driven price surge. (Terrapin Construction Group, 6 November 2026)
NextMSC modelled the tariff exposure on a reference US$1.13 billion, 100-megawatt facility and found that a scenario assuming 50% imported steel content implies approximately US$39.6 million in Section 232 exposure โ equivalent to 3.5% of facility cost. At the lower, 10% applicable rate available to domestically melted and poured steel, the same exposure falls to US$15.8 million, an 80% reduction, if origin documentation qualifies. NextMSC noted that transformer lead times of approximately 36 months and skilled-labour shortages weigh more for most projects than the tariff alone. (NextMSC, 1 October 2026)
The scale of the AI infrastructure build makes even marginal cost increases material for investors. The Boston Globe reported on 26 October 2026, citing Goldman Sachs data, that Amazon, Meta, Google, Microsoft and Oracle combined were on track to spend more than US$800 billion on capital projects in 2026, with capital expenditure expected to reach US$1.2 trillion in 2027. Bloomberg's cost estimates, referenced in the same article, put steel prices at their highest since 2022 and copper close to a record. Columbia Business School economist Stijn Van Nieuwerburgh, in an October 2026 National Bureau of Economic Research working paper, calculated that AI infrastructure spending would average 3.2% of US gross domestic product annually from 2025 through 2032, and that US data centres coming online through 2032 would cost a cumulative US$9 trillion. (The Boston Globe, 26 October 2026)
Canadian counter-tariffs on US imports have added an average of 1.7% to North American commercial real estate construction costs, CoStar News reported on 24 November 2026, citing a Cushman & Wakefield Canada analysis. The increase is tied principally to steel and aluminium. Cushman & Wakefield Canada's own published report, based on data as of 21 May 2026, estimated that tariff exposure raises construction materials costs by 9.2% on average, with total project costs rising by 0.92% โ and characterised the resulting higher cost environment as "a new cost baseline" rather than a temporary disruption. (CoStar News, 24 November 2026; Cushman & Wakefield Canada, 21 May 2026)
Asian Mills Reroute: Korea and Vietnam Fill the Gap
While overall US finished steel imports are down, Asian exporters with existing quota arrangements have captured a rising share of a shrunken market. The American Iron and Steel Institute (AISI), in its October SIMA import data released on 6 November 2026, reported that South Korea had filed import permit applications totalling 3,900,000 net tons in the first ten months of 2026, up 68% from the same period in 2025, making it the largest source of US steel imports by volume. Vietnam filed for 213,000 net tons in October alone, up 119% from September final imports โ the highest monthly percentage jump of any top-five supplier. (American Iron and Steel Institute (AISI), 6 November 2026)
Jiangsu Sushang Steel Group's industry analysis, published on 23 November 2026 and drawing on US Commerce Department SIMA data, found that US finished steel imports fell 22.8% year on year in the first half of 2026, while South Korea's exports to the US surged 37.4% over the same period to nearly 1.99 million short tons. Vietnam posted a 57.2% year-on-year increase in US-bound exports. The analysis noted that POSCO and other Korean mills were specifically delivering steel for data-centre infrastructure, hot-rolled coils and selected tubular goods. Canada, by contrast, saw exports to the US decline 44% year on year in H1 2026, with Brazil down 41.7% and Mexico down 37.2%. (Jiangsu Sushang Steel Group (JSSS Steel), 23 November 2026)
POSCO Holdings reported third-quarter 2026 operating profit of KRW 945 billion, up 47.9% year on year and 15% quarter on quarter, according to Seoul Economic Daily on 2 November 2026. The steel division posted approximately KRW 455 billion in operating profit at a margin of 4.6%, up from 2.9% in the second quarter of 2026, with higher selling prices, improved volumes and cost controls cited as drivers. The profit came despite US-side countervailing duties of 3.7% that the US Commerce Department finalised on POSCO in May 2026, according to KED Global, and amid the US steel industry's formal request to the administration in September 2026, reported by AISI, for a country-specific tariff-rate quota on Korean steel to curb the import surge. (Seoul Economic Daily, 2 November 2026; KED Global, 19 May 2026)
Capital Implications: Budgets, Bonds and the Import Arbitrage
AISI's October SIMA data, released on 6 November 2026, showed that total finished steel imports were down 10% and overall steel imports down 6% in the first ten months of 2026 relative to the same period in 2025. The estimated finished steel import market share was 17% year to date and 18% in October โ a share that AISI noted was running above the 16% recorded in its year-to-date figure through September. The underlying dynamic โ fewer overall tons but a higher share going to finished rather than semi-finished product โ reflects buyers managing cost by routing around the highest tariff tiers where possible, including by importing semi-finished billets and slabs, which the JSSS analysis noted edged up 2.4% in H1 2026, to bypass finished-goods tariff exposure. (American Iron and Steel Institute (AISI), 6 November 2026; Jiangsu Sushang Steel Group (JSSS Steel), 23 November 2026)
For hyperscale developers and sovereign-fund-backed campus builders pricing multi-hundred-megawatt facilities, the structural steel cost surge intersects directly with capital market scrutiny. The Boston Globe reported on 26 October 2026 that bonds backing data-centre projects had fallen in value and that the Nasdaq had declined nearly 6% from its October peak, as investors assessed return assumptions on AI infrastructure. Columbia University's Van Nieuwerburgh noted that the cumulative data-centre pipeline through 2032 would need to generate approximately US$3.5 trillion in revenue per year to earn a 10% return โ equivalent to nearly 9% of projected 2032 US GDP โ and that outside investors and lenders would supply more than half of the roughly US$2.9 trillion in finance required through 2028, citing a Morgan Stanley estimate. (The Boston Globe, 26 October 2026)
Cushman & Wakefield Canada warned in its published tariff analysis that historical construction cost and feasibility assumptions are no longer valid reference points, and that budgets, return thresholds and contingencies across the North American commercial real estate and infrastructure sectors must be recalibrated to account for what it described as "a structurally higher cost environment" โ one in which the remaining tariff architecture on steel and aluminium is "both layered and durable". Procurement teams sourcing steel for data-centre structural frames face a binary between domestic mills pricing at multi-year highs and Korean or Vietnamese tonnage subject to quota scrutiny, anti-circumvention enforcement risk and lengthening lead times. (Cushman & Wakefield Canada, 21 May 2026)
The Friday Digest
Enjoyed this? Get the week's top business stories, every Friday.
Free. One email a week. Unsubscribe in one click.

Written by
TPC Editorial Desk
The Platinum Capital editorial desk
Articles on The Platinum Capital are produced by the TPC editorial desk using AI tools and are fact-checked against public sources. Profiles are based on information provided by the subject. Reach out at info@theplatinumcapital.com.